Hello team,

Schedule dates not appeared in planned order Sap . Through some light on this

Thank you in advance

Venkat

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You need to either run MRP with parameter Scheduling = 2 or to manually schedule the planned order in transaction MD12, by clicking the respective button. If, by any chance, the order is not scheduled, you can check for error messages in the scheduling log.

Regards,

Caetano