Hi All

I have created a schedule agreement with LP.

I have also created delivery schedule for this.

Now while trying to do MIGO against this schedule agreement number , it is giving error , no selectable items.

What can be the possible chances for this?

Kindly advise.

regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi PVS,

check the GR date,

if it is prior to the schedule date it will give this error,

check the SA is released or not,

reward if useful

lakshmi reddy

Answers (6)

Answers (6)

Former Member
0 Kudos

Check whether 1) the Purchase order is released

2) Already GRN might happen

G.Ganesh Kumar

Former Member
0 Kudos

if the MIGO date is earlier than the Schedule date, then it will show this error.

put the schedule date same as MIGO date, it will accept.

Former Member
0 Kudos

Dear PVS,

Please check whether deliver schedule lines are released.

GR date is on or after schedule line date.

System will not allow GR before schedule line date.

Reward if useful,

Vivek Maitra

Former Member
0 Kudos

Dear all

Kindly check in T.Code:-Me38,Schedule date mentioned should be past date of GRN date.

Edited by: Chandra Mohan on Dec 28, 2007 9:52 AM

Former Member
0 Kudos

Hi,

check whether vendor confirmation is reqd before migo and that u will do in VL31N.

and start delivery date in del schedule.

Thanks

Suresh

Former Member
0 Kudos

Hi,

Maintain delivery schedule for today's date, then only you will be able to proceed the Goods Receipt.

Regards,