on 11-03-2020 4:33 AM
We are running a profitability analysis realignment (app "run realignment, profitability analysis) and with these 2 cases:
1. Changing a product master data characteristic and running the realignment afterwards.
2. Not changing the product MD itself but giving a specific value in input during realignment.
I would like to know if the realignment can be limited to a specific period of time? in the selection parameters I only see fiscal year as possible select or posting date, but I do not see how to limit the change to a specific month (for example).
There are a few date for Profitability Realignment.
1. Fiscal year
2. Posting Data
3. Realignment Data
based on that, there is result based on different Realignment year/month.
you might want to check the attached sample result list.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
9 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.