multi maintenance package plan not scheduling correctly

bob_danley
Explorer
0 Kudos

Hi Everyone,

I have been asked by a business user to schedule a plan with 4 operations in the task list, which all have different maintenance packages and hiearchies assigned to come out in consecutive order and repeat itself.

I have tried configuring offsets in the maintenance strategy packages with no success.

any help in figuring this out would be greatly appreciated. 

example

operation 1- maintenance package 1 month, hierarchy h1

operation 2- maintenance package 2 month, hierarchy h2

operation 3-maintenance package 3 month, hierarchy h3

operation 4-maintenance package 4 month, hierarchy h4

when scheduling the plan

SAP will not rotate the packages consecutively

example:
ip10 scheduling

1m

2m

3m

4m

1m

4m

1m

3m

2m

we would like the plan to generate like this

1m

2m

3m

4m

1m

2m

3m

4m

View Entire Topic
AndrewSpring
Explorer
0 Kudos

Screen shots for 300-600-900 Scheduling