on 05-28-2011 9:22 AM
Dear Experts,
We required MRP at Company code level.
We have 33 plants for MRP run , While running MRP system has to consider Finish Goods stocks of all plant's location should be consider for Availiblity check
MRP run carried with scope of planning , in this scope of planning all the
required plants are assigned , during planning Run , the stocks at other
plants are not consider during NET requirement calculation.
In turn it creates the planned independent requirement directly.
So kindly suggest where we are going wroung.
Thanks
Material with scope of planning for all required plants.
1. material with MRP type --- PD
2.procurement type --- F and X (since planning external )
3.Planning strategy --10
Hi Don,
DB49 is right.
Having 33 plants makes a complex supply chain, therefore I also suggest that you take a look at what SAP-APO can offer you in terms of complex supply chain planning functionality. It is designed for cases like yours!
Regards,
Mario
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.