Material has MRP type ND (no planning)assigned and there is no stock in system but if we create sales order then system still confirm sales order qty. Do you know what could be the reason?
Thanks.
Hi Eric,
I guess the lead time in the material master is "0" & in scope of check (Transaction OVZ9) "Check without RLT" check box is not selected. In this case system will confirm all orders for today's date.
Please select this check box & then check the order.