on 2014 Aug 12 12:26 PM
Hi Guru's,
As per my business scenario, i am creating project with WBSE, Activities and BOM.
By using the reference points, i am transferring the BOM to Project, then executing MRP run (MD51).
But after MRP run i found that multiple PR's generated for the same Material.
Please find my BOM structure
BOM-->Assembly + raw material
Assembly is consists of
Sub-Assembly+ 2 raw materials
Sub-Assembly consists of
1 Raw Material.
as per this i should have 4 PR's after MRP but system is generating 8 PR's.
Please tell me where i am doing wrong
Regards,
Rao
Hello,
Greetings of the day !!
Double PR has been generated after MRP run. Although the material which got two PR generated had got only 1 dependent requirement.
We have maintained one material data as Procurement type as F & Special procurement blank For other material, Procurement type as F & Special procurement 30.
Can anyone help me on this which is top Priority?
Thank You.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
8 | |
6 | |
5 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.