on 01-10-2023 5:32 PM
hello,
in our case, availability check is configured:
Though, while running mass availability check via COHV (reset and run material availability check) for both planned orders and production orders, only the production orders get confirmed committed components.
example via CO09:
Can someone explain to me how can i get the planned orders availability check executed via COHV. Is it a missing configuration?
thanks
hi Jacob, thanks but these paths do not exist in S/4 HANA:
SPRO > Production > Capacity Planning > Availability Check > Define Availability Check Rules) to ensure that the correct availability check rule (PP) is assigned to planned orders.
SPRO > Production > Capacity Planning > Availability Check > Define Mass Availability Check) to ensure that the planned orders are included in the mass availability check.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
8 | |
6 | |
5 | |
5 | |
4 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.