Order Reservation number linked to sales order

primax12
Explorer
0 Kudos

Hello together, 

I have a question which is for the most users allegedly easy. I have a material number xyz for which I'm checking transaction md04. Material xyz is part of a module wxyz wchich is again part of a finished good vwxyz. 

In md04 i only cann see in listoverview the order reservation number and material number of module wxyz. 

Is there any possibilty (other transaction) in which I can see that this material xyz is actualy reserved for a specific sales oder of finished good vwxyz. 

Thanks in advance. 

Accepted Solutions (0)

Answers (1)

Answers (1)

DominikTylczyn
Active Contributor
0 Kudos

Hello @primax12 

Unless you work in MTO environment, there is no direct static link between a procurement MRP element (planned order, purchase requisition, production order, purchase order etc.) and corresponding requirements. 

However, you can identify corresponding requirements with the pegging function - SAP Help Pegged Requirements

loiofda0cf53c6744608e10000000a174cb4_LowRes

Best regards

Dominik Tylczynski