Hi all,

    I meet another problem, for finish-goods A, we want to create on it, and sales it. But another material B is the same as A, that means in our company we can use B to replace A totally.  I thought of follow up setting in material master, we use it on component now .

    My question is,  can we set B as the follow-up material in A?  Then when we create PIR on A, MRP can general B plan order while A  stock is not enough.   Please advise, thanks.

BR,

Microfish

Accepted Solutions (0)

Answers (1)

Answers (1)

sandeep_praharaj
Contributor
0 Kudos

Hi

Yes system will generate planned order for Set B prior to material master setting user have to maintain bom with follow up & discontinue material.

Kindly refer below link for more clarification

http://scn.sap.com/docs/DOC-53212

If any query kindly revert.

Thanks & Regards

Sandeep Kumar Praharaj

former_member611794
Participant
0 Kudos

Hi Sandeep,

    Thanks for your reply, this document is very detail about follow-up function, and is very helpful for new people to know follow-up.

    But this is not directly answer my question.

BR,

Microfish

sandeep_praharaj
Contributor
0 Kudos

Hi,

  I have given answer to your question please find the screenshot .

also  kindly specify what direct answer you need what is your question for which you need direct answer.

Thanks & Regards

Sandeep Kumar Praharaj

former_member611794
Participant
0 Kudos

Hi Sandeep,

    I want to use it on finish-goods, not on BOM.

BR,

Microfish

sandeep_praharaj
Contributor
0 Kudos

Hi,

you have to maintain in BOM because MRP planning will happen as per BOM. mean time you can test it,

I have tested it with out maintaining BOM it is not happening.

If any query kindly revert.

Thanks & Regards

Sandeep Kumar Praharaj

former_member611794
Participant
0 Kudos

Hi Sandeep,

     Yes, if A & B not in BOM, my testing also is not happening.

     Is there any other method ?  Thanks.

BR,

Microfish

sandeep_praharaj
Contributor
0 Kudos

Hi,

  it is not possible in standard without maintaining BOM.

kindly check for any enhancement to build logic on MRP run .

Thanks & Regards

Sandeep Kumar praharaj