I'd like to change the reach of PIR for a material, where to do that?

Current = 11, would like to change to 16 / 24

JulianoRomanato
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello mook.

How are you? Could you please answer which is the application that you are using.

Regards.

Juliano Romanato.

Martijn_Mook
Explorer
0 Kudos

Hello Juliano,

The application I'm using in the screenshot is Maintain PIR, however I don't think you can change it there.

Martijn

Accepted Solutions (1)

Accepted Solutions (1)

Mateus_Blume
Product and Topic Expert
Product and Topic Expert

Hi,

In 'Maintain PIRs' app, when directly clicking into the material only 6 months’ PIRs can be displayed and edited, this is the standard behavior of the app. However, if you first tick the material and then click the “edit” button to get into the material, you can adjust the start time of the planning period at your will and maintain the PIRs in the next months.

Another option's to use the 'Change PIRs' app, you can just enter the planning horizon in the initial screen.

After PIRs are maintained, the 'reach' will be updated according to the number of PIRs maintained.

Thanks and regards,

Mateus Blume.

Martijn_Mook
Explorer

Thanks Mateus, this worked. Appreciate it!