on 2021 Dec 14 10:19 AM
Hi,
In 'Maintain PIRs' app, when directly clicking into the material only 6 months’ PIRs can be displayed and edited, this is the standard behavior of the app. However, if you first tick the material and then click the “edit” button to get into the material, you can adjust the start time of the planning period at your will and maintain the PIRs in the next months.
Another option's to use the 'Change PIRs' app, you can just enter the planning horizon in the initial screen.
After PIRs are maintained, the 'reach' will be updated according to the number of PIRs maintained.
Thanks and regards,
Mateus Blume.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Mateus, this worked. Appreciate it!