Hi All,
I am facing this issue while creating the sales order. The plant in which the order is being created has enough unrestricted stock as on today's date but the the materials availability date that is being proposed is in the future. Can you please suggest.
Regards
Deepak
Hi Deepak,
Please check in CO09, the stock is free or reserved any Sales order or Delivery document.
Share me the CO09 screen shot.
Thanks
Vikas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Everybody,
Thanks for all the replies. I had made a really stupid mistake. The trasportation planning lead time was 2 days due to which the material was not etting confirmed on todays date. I removed the value of days from the trasportation planning lead time in the route and the system confirmed the MAD as todays date.
I would like to thank everybody again for taking time to look into the issue.
Regards
Deepak
Hi,
Please check in MM02 (MRP fields) also.
Thanks,
Kamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you need to check any lead time is maintained in the sales document type and also check the settings of scheduling both for sales documents and shipping points under
LE-Shipping-Basic Shipping functions-Delivery Scheduling and Transportation Scheduling
The settings need to be unmarked for the above
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
9 | |
7 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.