Dear experts
We've configured the synchronizing of PM x AA.
in our scenario, during the creation of the equipment (IE01), the fixed asset is created (AS01)
However there are mandatory fields in Asset MD which needs to be filled, but when the a...
Dear gurus,Is there a function to get baseline date (not the one stored in RBKP/BSEG...but rather a function to calculate it)?I've checked these functions...but none of these are the one consider - for example - fixed days and additional months (from...
Hello Gustavo,Unfortunatelly both FM have the field ZFBDT (baseline date) as one of the importing parameters (thus they do not calculate it...)Nevertheless, thank you for your cooperation
Hello Gustavo,Actually 'day limit' and 'additional months' fields are both in a area of OBB8 related to "baseline date calculation", therefore they impact only baseline date directly (not the net due date)In order to calculate the 'Net due date' the ...
Hello Gustavo,I believe there is more to the calculation of baseline date. Example: Baseline date also suffers impact from the Day limit (ZTAGG), fixed days (ZFAEL) and additional months (ZMONA), as you may check in OBB8.This function "FI_BASELINEDAT...