HI,
i am procuring the material as per below:
Material Price Rs.100/mt
Qty: 5
CGST - 12.50 Rs.
SGST - 12.50 Rs.
GST compensation Cess (Non Deductable) - 400 Rs./MT
Entry at the time of MIGO -
Stock A/c Dr. 2500/-
GR/IR Clearing A/...
Hi,
1, where we can assign the external number range in Quota Arrangement?
2. Role of Multiple internal number range for Quota Arrangement?
3. Where can we define the screen layout for Quota Arrangment?
Regards
Nitin
import-process.txtHi,
i have created one Import PO and maintained one custom condition, since custom condition condition will not be added in material price therefore i also maintained one similar condition in negative.
now when i doing MIGO then...
Hi,In my Company TAXINJ procedure is used.When i extended the material in new plant then system is not calculating the tax while in existing PO system is calculating the tax.second when i create the new material then also system is also not calculati...
Hi,when we do Subsequent adjustment for Subcontracting in MIGO wherein Subcontractor use 1 more qty as comapre to mentioned in BOM.then Accounting entry would beConsumption A/c Dr - 1500/- Stock A/c Cr - 1500/-pls explain me the same cost w...
Hi, vend
our import scenario is working fine. but the above is domestic scenario, our company is procuring the material from a trader.
In this case i maintained condition record for ZIQN.
So, ZIQN is appearing in PO itself and getting inventor...
Hi,sorry i am not authorize to read prasoon noteMy question is for Example:Material A which subcontractor return us maintained at MAPwe send the material B to subcontractor which is also maintained at MAP and price is Rs.50 eachTo make one pieces of...
Hi,Thanks Rosh for detailed reply.The same i am saying, I think system is assigning in a right way, because after assigning to Vendor A and B, remaining quantity is 300 pieces that will not be split. Therefore system will search for the vendor who is...