Hello,I have a First process which manufacture the Tire(Production line-1), once tire is produced then only can make the Car(FG).(Production line -2).May i know how can i map this process in SAP connecting together?Thanks,Shri
Need an option on improvement on to reduce average time for PR to PO creation process.
1. Systematically how to make it fast action?
2.How to steam line the business process?
3.is there any report shows the PR to PO process time line.
Thanks
Hello,
We did some change in Consignment process price.These changes created a situation where the MM balance and SAP GL balances no longer matching. Over the period of about 4 months, this grew from $0 to $10K difference between the GL and MM. It ...
Hello,
I have near about 50 PR types due to various department for approval purpose.
and screen and functionality looks all same.
Now we want to remove all PR types and have only one PR type..
How will approach this?
Thanks,
SS
1.Above answer is for systematically i can do.2. In terms of business process, how can i imporve?3.Is there any report shows the PR to PO creation time line?
Thanks Sanil.The main problem is, For consignment movement type 412, reversing
amounts based on pricing condition instead of material document.that causes the difference.
Really appreciate your answer.1.We know the material and GL also we corrected the new posting as well.It is for old posting.2.We did not change any OBYC setting so far.3.It was happened in Feb20, Now we cannot reverse the posting since MM and FI peri...