Hi,
We have following scenario.
For material RM04 there are three batches with expiry date as below:
Batch Min shelf life Max shelf life Qty
001 1sept 12 1oct 12 100
002 1oct 12 1 nov 12 100
003 1nov 12 1 dec 12 100
System is configured for planning based on maximum shelf life date. There is a requirement element of 150 quantity with required date as 3rd Nov12.
In this case system shall consume batch 001 & 002 first as they are near to their expiry. So system shall allocate 100 qty from batch 001 & 50 from 002.
But what we found after heuristic run is system allocating batch 003 first with 100 quantity then batch 002 for 50.
How can we meet the requirement? i.e. batches near expiry shall consume first.
Please let us know is you faced simillar problem...
Regards
Nikhil
Please consider the req element date as 10th of september in above case instead of 3rd of november12.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.