SAP APO
I am creating Purchase requisition in APO and Cif it to ECC. I want to change few date fields logic in ECC before it gets created in ECC.
Fields which I want to change in ECC : Requested date, Delivery date, Released date based on GR proc time and Pl.Delvery time.
Please suggest a way for this customization.
Hello,
check the Enhancement= CIFPUR02 component EXIT_SAPLMEPI_005 in the transaction SMOD at the ERP side.
You can use user exit 'SAPLMEPI_EXIT_005' to transfer customer-specific fields from the APO system into the purchase requisition in the R/3 system (table EBAN, INCLUDE 'CI_EBANDB').
For more information, see SAP Note: 371037
Best Regards
Gergely
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
5 | |
4 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.