Hi everyone,
Since the beginning of the year, we have been using the embedded SAP Transportation Management System. We have implemented SAP Note 1763253 to consider the BP goods receiving hours instead of the calendar resource.
Now our SAP users complain that they have to maintain the goods receiving hours in two different tabs in the Business Partner.
For the Available-to-promise check they have to maintain the goods receiving hours under business partner role ‘Customer’ tab ‘Customer: Unloading Points’.
For the Transportation Management System they have to maintain the goods receiving hours under role ‘General Business Partner’ tab ‘Control’. In thise area we have far more options than under 'Customer: Unloading Points'. Here, for example, we can maintain exceptions.
Is there a solution from SAP to ensure that the ATP and the TM work smoothly together? It is currently very unsatisfactory that different master data objects are used. Unfortunately, this leads to mistakes and problems in users day-to-day work.
Request clarification before answering.
Hello @tberner
That is another point where TM is more embedded than integrated. I had a similar situation with SD routes and TM default routes - they have to be consistent to provide smooth integration between sales orders and TM planning. However they are completely independent settings and a custom report had to be developed.
In my opinion your best bet is a custom enhancement to validate BP data or to synchronize SD and TM receiving hours. I would not count on having that delivered that in standard soon.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
4 | |
3 | |
2 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.