02-02-2015 7:33 AM
Hello all,
I have made some enhancements in SMOD and assign to the same project, I transport TR for each enhancement from development to testing environment, the first two enhancements are working fine in testing system, but then I made an additional enhancement and assign to the project, it does not work in testing system after transport the TR. I checked CMOD in testing, the enhancement assignment is missing while in development system the assignment exists.
In development system 6 enhancements are activated in project ZQM
In testing system only the first two enhancements are activated in the same project
The enhancement itself is active in testing system
02-02-2015 7:38 AM
Hi,
Did you checked whether the component is activated in target system for the other 4 enhancement?
02-02-2015 7:38 AM
Hi,
Did you checked whether the component is activated in target system for the other 4 enhancement?
02-02-2015 7:46 AM
Hi Jayanthi,
The other 4 enhancements all are not activated in target system.
02-02-2015 7:50 AM
Hi Danny,
The project is transported to testing client in your second TR?
02-02-2015 8:26 AM
Hi Archana,
I think the project is transported along with the transporting of the first enhancement.
Regards
Danny
02-02-2015 8:31 AM
Hi Danny,
but then I made an additional enhancement and assign to the project
So, as per this you assigned additional enhancements to this project. So, if you want to see this assignment in testing client, you will need to move project to testing client again with changed assignment.
As mentioned below by me, you can add the project to TR using tcode se03 -> Include Objects in a Transport Request -> using object 'R3TR' 'CMOD' Project.
02-02-2015 8:56 AM
Hi,
You can do the same by using GO To->Object directory entry in CMOD for the project.
02-02-2015 9:32 AM
Hi Archana,
Do you mean the screenshot below? Do I need to enter project name in the blank field?
02-02-2015 10:25 AM
Hi Danny,
Yes. You will need to enter project name in blank field and execute. Then you can give your TR number in which you want to save the project. Then, you can move this TR to testing client.
02-02-2015 8:00 AM
Hi,
Try deactivate the project again and then once again activate component in the enhancement and then activate the project once again and send the transport of the project as well to target system along with enhancement and Component.
02-02-2015 8:19 AM
Hi Jayanthi,
Deactivating the project does not generate transport request, how can I send it to target system?
Danny
02-02-2015 8:25 AM
Hi Danny,
You can add the project to TR using tcode se03 using 'R3TR' 'CMOD' Project.
02-02-2015 8:31 AM
As your project has already been transported, that may indicate that the project is locked in a unreleased transport request, could you look for such a request with SE03, Search for Objects in Requests/Tasks (R3TR CMOD project)
Regards,
Raymond
02-02-2015 8:13 AM
Check sequence of transport import vs sequence of transport release, seems the last import transported an older/outdated version of the project activation. (Object R3TR CMOD <project name>)
Regards,
Raymond