HI All,

I am moving master data from client to client using ale setup. Almost all the data was moved. Now i want to move work center and routing. I created a model view for work center IWKCE) and routing with LOIROU. I want to know the tcode like bd 10 to send these two master data. I tried with tcodes like POIM and but i am not bale to send with this. Please give me some idea how to solve this.if this is not possible with ale i will upload through LSMW.

Regards,

Madhu.

Edited by: madhurao123 on Jun 29, 2011 10:51 AM

7 REPLIES 7

JL23
Active Contributor

0 Kudos

Hi Jurgen,

I have seen this tcode. I tried by giving the Optimization system ( i given here the receiver system) and i selected work center box and i passed there work center and plant. Before i created a model view with IWKCEN. When i am sending the work center through poim it is giving an information message like 0 IDocs were generated (according to selection . Is there ant more settings need. Here in out bound parameter i used message type IWKCEN and basic type as IWKCEN01. In receiver system i used message type as IWKCEN and process code as bapi . is there any settings i have to change.

Regards,

Madhu.

JL23
Active Contributor
0 Kudos

Looks like some IDOCs cannot be used for ALE import to SAP ERP system.

see details in Note 198252 - Special features of POI message category LOI*

Detailed docu can be found in attachments to OSS Note 538945 - FAQ: POI interface, transactions and message categories

0 Kudos

HI Jurgen,

By using the reports RCRAPDX1 and RCRAPDX2 i successfully moved the data.

Regards,

Madhu.

madhu_vadlamani
Active Contributor
0 Kudos

Using the reports issue solved.

0 Kudos

Hello,

I have the same problem to move work center and routing.

You have moved work centers with report RCRAPDX1 and RCRAPDX2.

But how did you move routing?

Thanks

0 Kudos

Hi Arnfried,

I moved that data with RCPTRA01. Check the documentation of this program for further information. Check and post if need help. I think it is better to post as a new thread.

Regards,