cancel
Showing results for 
Search instead for 
Did you mean: 

Write Optimized DSO

Former Member
0 Kudos

Dear All,

We are using the Write Optimized DSO and again we are loading data to some standard DSO.

Now we need to create the process chain.

My doubt is do we need to include actiivate DSO step after write optimized DSO or not in the process chain.

Please help me.

Thanks,

Saveen Kumar

Accepted Solutions (1)

Accepted Solutions (1)

mr_v
Active Contributor
0 Kudos

Activation is NOT required for W.O.DSO.. So NO need to include activation step in process chain

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks for the help.

Former Member
0 Kudos

Hi Saveen,

Once the Data is loaded into Write optimized DSO, the data will be immediately available for further data loading. This is the advantage of write optimized over the other DSO's. So no need of activation.

Regards,

Pavan