cancel
Showing results for 
Search instead for 
Did you mean: 

Value Mapping in BPM

Former Member
0 Kudos
71

We are using Value Mapping in XI 3.0 in the integration builder under the configuration.

Value Mapping is not working during the transformation step in BPM. See help.sap.com under transformation step: http://help.sap.com/saphelp_nw04/helpdata/en/14/80243b4a66ae0ce10000000a11402f/frameset.htm

Does anybody have a solution for executing the value mapping in this case.

Thanks in advance,

Glenn van Kamperdijk

Accepted Solutions (0)

Answers (1)

Answers (1)

stefan_grube
Active Contributor
0 Kudos

Just do the value mapping on the message, before it arrives the BPM.

For performance issues, you should do as much mapping outside the BPM as possible.

Stefan

Former Member
0 Kudos

Dear Stefan,

What if you do want to use value mapping in a ccBPM? What values should be entered at:

Source Values For Agency?

and

Target Values For Agency?

Best regards,

Roelof Jan