Dear all,

I have moved tranport request from DEV to QA and to PRod .

Transport has been successfully done on QA and Prod .

I have checked transport request log in SE01.

I got the below log :

IRQ System IRQ

Selection for Import 16.04.2010 14:36:07 (0) Successfully Completed

Import ABAP Dictionary Objects 03.05.2010 10:22:21 (0) Successfully Completed

ABAP Dictionary Activation 03.05.2010 10:22:25 (8) Ended with errors

Import 03.05.2010 10:22:32 (0) Successfully Completed

Check Versions 03.05.2010 10:22:34 (0) Successfully Completed

Generation of Programs and Screens 03.05.2010 10:22:36 (8) Ended with errors

Transferring System 06.05.2010 15:03:59 (0) Successfully Completed

Import steps not specific to transport request

IRP Production

Selection for Import 03.05.2010 10:22:32 (0) Successfully Completed

Copy File Between Transport Groups 06.05.2010 15:03:59 (0) Successfully Completed

Import ABAP Dictionary Objects 24.05.2010 16:07:49 (0) Successfully Completed

Import 24.05.2010 16:07:57 (0) Successfully Completed

ABAP Dictionary Activation 24.05.2010 16:08:27 (8) Ended with errors

Check Versions 24.05.2010 16:08:36 (0) Successfully Completed

Generation of Programs and Screens 24.05.2010 16:08:39 (8) Ended with errors

Import steps not specific to transport request

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Is this a new installation?

Did you run SGEN (at least once) after installation ?

Try to import this request with overwrite originals option and paste the result.

Regards,

Nick Loy

former_member204746
Active Contributor
0 Kudos

check contents of F:/usr/sap/trans/tmp/IRDA905202.IRQ

Former Member
0 Kudos
Generation of Programs and Screens 24.05.2010 16:08:39 (8) Ended with errors

Seems issue is not related to configuration.....just re -check all dependancy objects have transported to IRP system or not?

System is unable to generate some of the screens....just click on the above error line, then you will find the exact reason, why generation is not happening.

Regards,

Nick Loy

Former Member
0 Kudos

Hi Nick ,

I have Double click Generation of Programs and Screens 24.05.2010 16:08:39 (8) Ended with errors and I got the log .

######################################

Generation of programs and screens

Transport request : IRDK905202

System : IRQ

tp path : tp

Version and release: 372.04.36 700

Generation of programs and screens for transport request IRDK905202

Only generates programs with LOAD versions

Start on 03.05.10 at 10:22:36

Ended on 03.05.10 at 10:22:36

No. of programs /Min/Avg/Max (sec): 1 0 0 0

No. of screens /Min/Avg/Max (sec): 1 0 0 0

Generation of programs and screens

End date and time : 20100503102236

Ended with return code: ===> 8 <===

######################################

Kindly advise

Regards

Former Member
0 Kudos

Dear all,

Pls check the transport log :

######################################

ABAP Dictionary: Activation

Transport request : IRDK905202

System : IRQ

tp path : tp

Version and release: 372.04.36 700

Program start============================================================

Mass Activation

=========================================================================

Process..................: SAPDEVQA_8

User.....................: DDIC

Date, time...............: 03.05.2010, 10:22:23

Platform.................: CUSTOMER-IRQ(700)/ORACLE/AIX/SAPDEVQA

Tool.....................: BATCH/RADMASG0

Log......................: F, /usr/sap/trans/tmp/IRDA905202.IRQ

Program parameters:

Input Medium...............: Transp. Request IRDK905202

Activation Method..........: Inactv.

Chk Mode...................: T

Version to be activated....: M

Versions to be deleted.....: All versions are deleted

Lock Against Paral. Exec...: Shared

Independent Statistics Log.: being written

Parallel Mode..............: Switched on

..Resources................: 50% of Dialog Processes, Maximum 4 Processes

.Costs for Each Task.......: Minimum: 3.000, Maximum: 150.000

=========================================================================

*************************************************************************

Statistics on Activated and Deleted Objects

End phase 003 ***********************************************************

=========================================================================

Mass Activation

=========================================================================

Process..................: SAPDEVQA_8

Return code..............: 8

Phase 001..................: 00:00:01 (Object Activation)

Phase 002..................: < 1 sec. (Final log)

Phase 003..................: < 1 sec. (Statistics on Activated and ...)

Program runtime..........: 00:00:02

Date, time...............: 03.05.2010, 10:22:25

Program end==============================================================

ABAP Dictionary: Activation

End date and time : 20100503102225

Ended with return code: ===> 8 <===

Former Member
0 Kudos

Need more information to work on this.... if possible you need to paste the, alog and slog for the Transport in question.

SLOG: This log file provides the information on steps started by tp which have already run or in the process of running. SLOG is updated by tp.

ALOG: This log file provides the information what actions have performed when tp has started. ALOG also updated by tp. You can find out the tp action in Transport phase log (tp log).

You can get the same from usr/sap/trans/log directory ....