on 2012 Feb 16 7:29 AM
Hi All,
I have an issue with DSO activation when it runs using process chain, it fails throwing the error message "Process did not confirm within the permitted time period" but when we activate manually the DSO activates successfully. May I know what could be the reason for this issue.
Thanks,
M.Lakshmipathi
Hi Lakshmipathi,
Have u tried running the process chain anyother time other than usual time?.. still it fails ? ... it may nay be due to the fact that when the process chain is running its not able to get a available background process.
Regards
Venky
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try the below adjustments to the DataStoreobject parameters,
Please make the following adjustments in transaction RSODSO_SETTINGS
1) Maximum package size (for activation).
This you should reduce to 10000 (if the value is higher than that)
Then the package processing will be less time consuming.
2) Maximum wait time for process (for activation)
This could be increased to e.g. 600 (if the value is lower than this)
Thanks,
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
70 | |
11 | |
10 | |
10 | |
9 | |
9 | |
6 | |
6 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.