Hi all,

can anyone tell me what VBBE table is for. I want to pull data in this table to BW for infomation like "Inventory scheduled for delivery". I don't know the meaning of the fields like

material available date (MBDAT), VBELE, POSNE

some quantities like

OMENG, VMENG, UMREF

thanks,

Sabrina.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Sabrina,

VBBE is a table for Material Requirements Planning (MRP) – “Sales Requirements: Individual Records”.

Taking into account open sales orders R/3 using MRP calculates whether the ordered material with given quantity present in the company. If not, the system create planned orders for purchasing/manufacturing material needed. Taking into account duration of delivery from a vendor or duration of manufacturing the system calculates the material available date (MBDAT), i.e. the date when ordered material will present in the company.

Not sure about VBELE POSNE. May be it is a number (and item number within a doc) of the doc created by MRP (planned order) or it is a number of purchase order or production order generated on planned order.

OMENG – ‘Open qty in stockkeeping units for transferring reqs to MRP’ – the quantity of the required material, for example, in pallet, that will go to MRP process.

Not sure about the rest 2 fields.

Actually you need to go through description of MRP process for better understanding what is going on:

http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d27b744af11d182b40000e829fbfe/frameset.htm

http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d2ffb44af11d182b40000e829fbfe/frameset.htm

http://help.sap.com/saphelp_47x200/helpdata/en/c4/106953ae8a11d1a6720000e83235d4/frameset.htm

Best regards,

Eugene