Hello All,

The automatic status switch job is running after every import in our landscape. It is triggered even after quality or pre-production import jobs. It is looping through all the Change Documents even on what has just been created. This is unnecessarily making the job to run for several hundred seconds on regular basis. Is there any way to configure the job to only check Change Documents which are in a certain status for example, or to make it only run after the production import job? We have not found any option for this so far.

We are on Solman 7.2 SP08.

View Entire Topic
DinoPhilips
Participant
0 Kudos