on 2014 Dec 08 11:56 AM
Hi All,
I have transported all my targets my when i see in QAS system i am not finding any DS which i have transported
How to transport the source system?
Do i need to replicate all the data source again in QAS? after transporting.
Regards
Vickram
Hi,
This is the way to transport data sources.
Assuming as your landscape was in place
1. ECC dev system data source transport to ECC Qua.
2. Replicate ECC Qua data source into BW Qua.
3. BW Dev system data source transport to bw Qua. this makes BW Qua data source as active.
4. Remaing data flow you can transport form BW dev to Bw Qua.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vickram,
Yes you need to replicate datasources in QA and then ask your Basis team to reimport your datasource request.
Regards,
Ganesh Bothe
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
66 | |
10 | |
10 | |
10 | |
10 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.