Hi Gurus,

I am Extracting data from R/3 to BW, when i execute the infopackage the jobs in source system are in ready status and they are not moving to active & finished status.

Is there any method to make the jobs in source system active manually.

Thanks & Regards,

chinnu.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

did you check for processes are available to run this job in sm50 or sm51?

Regards

Sankar

Former Member
0 Kudos

When you execute the infocpackage you must use the inmediatly option for execution or programmed job ...in your case is assume that you use the orogrammed job....if you use this last option...you must setup your job with init time...if you do not use the start time and hour the job will never starts....this could be your problem

Former Member
0 Kudos

Hi Oscar,

Thanks for your reply. I used the option immediate.

Regards,