Simulation Option in Control of Setup Run ?

Former Member
0 Kudos

Hi Gurus,

I was trying to fillup the setup tables - OLI7BW for Sales Orders. I have never used the last option "Simulation Extr. Str. BW" option under Control of Setup Run and wondering if it is a helpful thing to use. Just curious to know what exactly does that function do ? My guess is, it does a simulation of filling up the setup tables instead of actually filling it up. If I'm right, where can I see this simulation status...I tried looking on the forum first but did not come across anything similar. Looking for your expert feedback.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

BW dev

You are right if you do this step before filling the tables it simulates. Its a good idea to do this before filling setup tables it shows if it has any errors. You could also directly load with out using this.

Thnaks

Sat

Former Member
0 Kudos

Sat,

I already knew that.. my question is, where can I see that simulation status or logs or something about that simulation happening ?

Former Member
0 Kudos

BW Dev

Please see the Logs Icon at the same place under Initialization.

Thnaks

sat

Former Member
0 Kudos

Thanks Sat.. although, is there something in the log that denotes that it was a simulation and not an actual run...