on 2007 Sep 27 2:00 PM
Hi All,
I need to develop a scenario MDM-XI-SAPR3 for vendor data.
I can not use CREMDM IDOC on R3 side as there is no process code for that. So client is expecting 2 IDOCs, CREMAS and ADRMAS.
On R3 side, first CREMAS creates vendor in R3 and then ADRMAS updates
Address corresponding to created vendor.
Now Source will be one XML from MDM (CREMDM) and XI will split it into
two IDOCs that are CREMAS and ADRMAS. But both the IDOC will get
triggered at the same time. So it will not be of any help as ADRMAS will
always go into error. Correct me if I am wrong.
So
Client suggested passing SERDAT IDOC. So now the question is we will
have to pass two records (CREMAS and ADRMAS) to this SERDAT IDOC. Now
these values will be hard coded in XI. But through Constant I can not
pass multiple values.
Because of these limitations on SAP Product, I am not able to go
ahead.
So I want a clarification on this. I should use the SERDAT IDOC or
not? If yes then how we can pass multiple values to it as through
constant we can not pass more than one.
Can you plz suggest?
Warm Regards,
Gouri
Hi Gouri,
>>>So it will not be of any help as ADRMAS will
always go into error. Correct me if I am wrong.
but you can just schedule restart IDOC report for IDOC - ADRMAS
and this should solve the issue right ?
Regards,
Michal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gouri,
please read SAP Note 1052964 carefully. It explains how-to send vendors from MDM to R/3.
BR Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
68 | |
8 | |
8 | |
7 | |
6 | |
6 | |
6 | |
6 | |
6 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.