Hi All,

Am new to SEP BPS.

Am trying the create the Manual Plannng. but it is giving the following message.

"Select a node related to tree".

I followed the steps mentioned below.

Selected the Planing LEvel, from planning menu selected the option manual planning --> create.

it gives me the above step.

The other alternative follwed is right click on the planning level, in the context menu it suppose to list the create manual planning. but am not able to see this option.

To create a manual plan any settings has to be done...

Regards,

Prathima.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Anurag,

Thanks for responding. Now am able to create. the problem

was the upper window was dragged till bottom.. so

am not able to see the bottom window.

Former Member
0 Kudos

if the response helped you can award points -:)

Former Member
0 Kudos

Hi Prathima,

To create Manual Planning, select the Planning package for the Planning Level and then select "Create Manual Planning"

alternatively

once you have selected the Planning package on the right click mouse of the planning functions also will give you the option to do the same.

Cheers