Dear SAP,

We are working to execute SAP Readiness Check and prepare to migrate to S/4HANA.

It shows that 3061414 - Enabling extended integration impact analysis for SAP Readiness Check can not be installed on our system. Is there a workaround to import this note?


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.
View Entire Topic
SAPSupport
Employee
Employee
0 Kudos

Dear Customer,

Please note that in order to perform the extended integration analysis as part of the Readiness Check, the ST-A/PI component version must be updated to 01U* SP02 (and implement SAP Note 3072059), or 01U* SP03+.

Please review the "Reasons and Prerequisites" section of note 3061414. There is currently no workaround available for this.