Hi All,

I have a requirement to come up with a report related to PS module.

the requirement is like this:

I have to report actual cost information for a given project, work order, WBS elements,

Activities and sub activities for each cost element (material, labor etc).

in SBC I am able to find cost information at Project, WBS element, activities and sub-activities in one Datasource.

and cost information at work order level in other data source.

I need to understand and establish a link between work orders and projects, how they are related and what linking is the linking object.

Any help from expert who worked in PS/PM/CO modules.

regards

Ram

Accepted Solutions (1)

Accepted Solutions (1)

former_member202718
Active Contributor
0 Kudos

Hi Ram,

Did u check the COEP table..if you are getting all the required data you need.

Check if you can create a Generic DS on that...

or

Talk to the FI/PS consultant and establish a link ...i.e a common field in both DS/Tables and on BW side do a look up and stamp the values...

rgds

SVU

Answers (1)

Answers (1)

0 Kudos

thanks guys. in my analysis It seems i got some clues..CO document number/item can make a link it seems.