cancel
Showing results for 
Search instead for 
Did you mean: 

Project Progress

Former Member
0 Kudos
65

Dear All,

Please suggest in case of my following scenario:

If I want to measure the project progress on the basis of work completed on each activities under several wbs and then total of project under which these WBS come.

I am using progress version with basis as Work. Assigning Degree of completion as measuring method to actual method in Progress Tab of each activity(Both Internal and external).

In CNE5 i get the correct % of work and weight for each activity.

But when I assign weight to the WBS above these activities and suppose there are three parallel WBS like this then I canot access the work done for each WBS.

As SAP does not allow % of work done for WBS.

Can somebody suggest something please.

Thanks in advance

Regards

Maneesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

None