Dear All,

I have a process chain in development system and it is scheduled for daily and It is working fine.

Now I need to make some changes in the process chain ie removing and adding one flow in the same process chain.

I am trying to delete it but again it is coming(not able to delete) .

What all steps I need to do before deleting the process chain.

Please help me.

Thanks,

Saveen Kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please follow the steps to modify the process chain

1. goto rspc1 >>> Planning mode >>> Deschedule the PC

2. Go to edit mode of the process chain

3. Right click on the link which you want remove and "remove the process"

4. if you want to add any steps in process chains > Go to process types and select

5. Once its done link with the process chain by drag and drop process

6. activate and schedule it to run as per your requirement

Regards.

Rambabu

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks All for the help.

Former Member
0 Kudos

Hi Saveen,

Goto your Process chain> Edit mode> right click on the process steps which you want to delete--> Remove process

Before doing this right click on the link connecting to this process step--> remove link

Then drag & drop the required process steps. link them in the correct sequence. Then Save & Activate the process chain.

Hope it helps!

Regards,

Pavan

Former Member
0 Kudos

Hi,

The process chain is suppose to run today by 5:30.

If i change in the process chain will it schedule.

Thanks,

SAveen

former_member181964
Active Contributor
0 Kudos

Hi,

Goto RSPC and double click on your PC and then click on Change Icon and then remove the unwanted Process Links and Processes and then add wanted ones and then save , activate and schedule.

Note: Right Click and Remove.

Thanks