What are the components req for tranporting a Process chain.

I have Infocube, InfoPkg, Infospoke and Infosource everything in QA.

The only thing which is not there is the Process chain, Mail varients, Start varient.

Should I add the Infopackage and all eventhough its already there ??

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hallo

I want to add one thing:

please make sure that you do not have the option Start Immediately otherwise after the transport the process chain will start. this is the standard as during the Transport the system activate and schedule the Process Chain.

Mike.

Former Member
0 Kudos

Ren, It is not required to move anything else except the process chains, Mail Variant, Start Variants and Process Variants.

Aslo, if I remember correctly the Process chains can be moved independently even thought the underlying objects are not already moved. The process chain only errors out at the time of activation in this case and there will be no issues at the time of transporting.