Process chain factory calender date

Former Member
0 Kudos
1,124

Hi All,

We have a process scheduled to run on specific time period. It is set with "do not run on Sundays and holidays" with factory calendar. PFA the snapshot


Can you please tell me where to see the holidays lists with date  maintained for the calendar ID.

Regards

Pradeep

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Pradeep,

Please see the be low step to see the holiday list

T-code = Scal

select factory calendar then click on display , below screen will open

click on display icon of calendar, then the below screen will be open

Select the year then select the display year i con on top, below screen will be displayed

Basically we will create the calendar in r/3 system from there we will replicate from transfer global settings

Regards,

Polu.

Former Member
0 Kudos

Thanks Anki

Answers (2)

Answers (2)

Former Member
0 Kudos

My suggestion is to create a dedicated factory calendar for the scheduling. You can indicate user-specific "working days" (i.e. days on which the process chain should run). The process chain in then scheduled against this factory calendar, periodicity is daily and special behavior "move to next working day".

You can define a factory calendar with t/code SCAL.

Please note 2 things:

1. Be careful to transport factory calendars because you will transport ALL factory calendars every time.

2. Normally the maintenance of factory calendars is effectuated in the (leading) OLTP system and synchronized / transferred to BW. It seems logical from a governance point-of-view to maintain also here the BW scheduling factory calendars.

Best regards,

RamanKorrapati
Active Contributor
0 Kudos

Hi,

T code - SCAL

Please search on Google by using search term as "Creating Factory/Holiday Calendar".

would be more useful.

Thanks

Former Member
0 Kudos

Hi Raman,

I don't want to create .I want to see the  holiday lists as per the calendar ID.

Also,I don't have access for SCAL

Regards

Pradeep

RamanKorrapati
Active Contributor
0 Kudos

please take basis/functional help.

They are the one who(FI/Functional team) maintained factory calendar data/holidays list.