Hi All,

One week back we have stopped Process Chain for 2LIS_03_BF for to load the entire datatill date) for Customized Cube which we created...

Actually it has data in R/3 Production from 1st August 2007 to till date.

As it is having heavy data in Production, first we have loaded to ZCube using filter Posting Date = 01.08.2007 to 31.12.2007 using Full Upload. Again we loaded data from 01.01.2008 to Till Date(21.04.2008) with Full Load.

We forgot to remove the Filter (01.01.2008 to Till Date(21.04.2008) after load done from IP Data selection tab.

Yesterday we have re-Scheduled the Process Chain for all cubes ( ZCube+ Standard Cubes).

Today we are getting the error Fatal Error and that filter is in Desiable mode

We want to execute the reqular delta's through Process Chains.. How to do it ?

Please very urgent

Your help will be appreciated..

Regards,

Kiran Telkar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

After running the full load, now run intilization with out data trasfer and then set the delta radio buttton. Now is rspc deactivater the rpocess chain remove the old infopackage and replace it with the new inforpackage.

Repeat this for all the data targets which are necessary,.