on 2009 May 20 11:56 PM
Hi,
I am into the process of Installing AS ABAP ECC6.0 on MSCS 2 node cluster (Win2003, MSSQL2005). While I am done with ASCS and First Node Installations, Database Intance setup halts at "Create / Modify Database schema prd" step with "the step CreateStdSchema with step key" error.
ERROR 2009-05-21 04:13:34
FCO-00011 The step CreateStdSchema with step key |NW_ABAP_DB|ind|ind|ind|ind|0|0|NW_CreateDBandLoad|ind|ind|ind|ind|8|0|NW_CreateDB|ind|ind|ind|ind|0|0|NW_MSS_DB|ind|ind|ind|ind|2|0|MssSchemaCreate|ind|ind|ind|ind|9|0|CreateStdSchema was executed with status ERROR .
Not sure if it has to do with Schema creation authorisation.Any help is greatly appreciated.
Regards
Habib
Hi,
What's the error that you're getting while creating the db schema?
Logs files would be a help.
thanks,
AB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I'm doing a Netweaver 7.10 instalation for Mobile and i'm facing this error.
Is there any solution?
I can't find anything.
Thanks in advance
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
77 | |
10 | |
10 | |
10 | |
10 | |
9 | |
8 | |
7 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.