How do you update the master data on a regular basis?

I did full updates for those as per the BP document. Should I have done deltas for those or should I just schedule the initial load to run at regular intervals?

I will never have much master data, however, it seems silly to do a full load every time.

Accepted Solutions (1)

Accepted Solutions (1)

former_member188975
Active Contributor
0 Kudos

Hi Stuart,

You could go either way...first you would have to see if the extractor supports the delta loading process. Another thing you need to look into is the frequency of load, which would be guided by the frequency of change to the master data in the source system.

We have deltas running for some major objects like customer, material, opportunities etc. A lot of them we manage with a weekly or fortnightly full load.

Hope this helps...