cancel
Showing results for 
Search instead for 
Did you mean: 

Master Data change

chris_robertson
Participant
0 Kudos

I've added a new attribute to 0Material and updated the update & transfer rules. My mind is fogging over now about the next step. What do I need to do to get this new field filled? We have 0Material set up with delta refreshes.

Thanks,

Chris

Accepted Solutions (1)

Accepted Solutions (1)

former_member188975
Active Contributor
0 Kudos

Hi Chris,

Even if delta loads are performed to 0MATERIAL, you can do a full load to bring in values for the new attribute.

Hope this helps...

Answers (1)

Answers (1)

chris_robertson
Participant
0 Kudos

Can I do a full data load without interupting the delta?

i.e. Can I do the full load then expect the delta to take care of it from there without having to re-init the delta's?

former_member188975
Active Contributor
0 Kudos

Hi Chris,

Try to set up the full load at a time so that its running will not clash with the delta load. The delta loads will continue as before and there is no need to do a ReInit.

Hope this helps...

chris_robertson
Participant
0 Kudos

Ok. This is what I was hoping to hear, but I was a little nervous to try it without a little reinforcement.

I'll give it a try.

Chris

chris_robertson
Participant
0 Kudos

This worked. I did the full load then the delta. Realized that I didn't update the update rule and went through the whole process again. Thanks for your input.