Dear All,

Hope you are doing good

Please help to resolve, as our client is using third part tool 3PL with middleware as SAP PI which sends inbound IDOC having purchase order, delivery detail to SAP ECC and it creates GR with movement type: 101.

A month back system was working correctly and now a days we are facing lot of inconsistencies like GR with movement type: 101 is created successfully, but inspection lots are generating sometimes and on other occasions it is not.

We tried to replicate in Quality and it works every time, the master data maintained in both system is exact as well as there is no master data changes w.r.t. to QM done in production system. The solution offered to business is to cancel the GR document with movement type 101 and again perform the GR, users do not want to go with this option and needs a sure shot way where inspection lot is generated every time.

Requesting to share the inputs to rectify this problem. Cannot upload any screenshots due to client server.

Kindly consider.

Thanks in advance.

View Entire Topic
rob_ariaans
Contributor
0 Kudos

Have you looked into authorizations?

RohitNAGDEVE
Discoverer
0 Kudos

Dear Sir,

Thanks a lot for reply.

Please see response inline.

Have you looked into authorizations? ---- 15 to 20 days back inspection lots were getting created, all of sudden it stopped.

rob_ariaans
Contributor
0 Kudos
Yes - so if no master data has been changed, and no customizing has been changed - then one of the few things left is authorizations. Did you check if any roles/role assignments has been changed?
RohitNAGDEVE
Discoverer
0 Kudos

Dear Sir,

Let me know check this with security team.