I am carrying out some work in a Sandbox and have schedule a Full Repair Load. It has loaded into PSA but is taking time to load to the target. Since it is Sandbox, can I cancel the load and if so could someone outline the steps thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi there,

If I understood correct you have the PSA already, so you need just kill the job for loading PSA into target in BW.

Hope this helps.

Weidong

Former Member
0 Kudos

Thanks where do I delete this from and how can I identify the job

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

If it a background job then u can cancel it in SM37-> select ur job name and from the menu-> Job-> Cancel Active job. Which kills ur job.

If it is working in foregroud then based on ur work process ID and PID u can choose ur job and then goto Menu-> Process-> u wil have two options 1] cancel with core 2] Cancel without core.

Cancel with core maintains a log file, u can check it in the AL11. and cancel wothout core wont contains a logfile. Which only cancels ur active job.

Later u can upload the data from ur PSA to ur DT.

Hope it hleps

Regards-

MM

Former Member
0 Kudos

Hi Niten,

You can find the job number from the infopackage. Now goto sm37 -> give the job id -> execute -> cancel the job.

You can later reload the data from the PSA to the data target.

Bye

Dinesh

Former Member
0 Kudos

From the Monitor screen for the Load in question go to the menu and select Environment -> Job Overview -> In the Data Warehouse. This will give you the Job related to this load to the Data Target.