on 2020 Apr 26 5:11 PM
Dear Experts,
I have requirement when BPM flow trigger a human task, The task approver needs to approver or reject the task, Task expiry time is 7days, I need to send total 3 reminder mail notification witha gap of 24 hrs ( likey reminder1, reminder2 and final reminder with this mail subjects lines).
I mean first reminder mail needs to send after 24 hrs, second reminder will after 48 hrs and final reminder will be after 72 hrs task assignment.
My problem statement:
The approver is approved the task after seeing the first reminder mail, Then i need to stop sending reminder mail 2 and reminder 3 mails flow and continue the BPM flow.
I tried the below blog. But not able to understand what the author implemented in the "IME " step inside of Event based choice.
Thanks in Advance
Pavan T
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
71 | |
10 | |
8 | |
7 | |
7 | |
6 | |
6 | |
6 | |
6 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.