Hello gurus!

I have a problem because some days ago there was a problem in PRD with the servers and a lot of resources went down. The thing is that this breakdown was when some workitems were executed. In the WF log the tasks where they were appear as "completed" but no other workitem was created and in the graphic log the line ends in some point between the completed task and the next one. Is there a way to reactiva these WF's??

Accepted Solutions (1)

Accepted Solutions (1)

former_member185167
Active Contributor
0 Kudos

Hello,

Can you see them in SWPR or SWPC? If so, restart them from there.

regards

Rick Bakker

hanabi technology

Answers (1)

Answers (1)

nabheetscn
Active Contributor
0 Kudos

The workflow must have hanged or errored out. Please use WF id in SWPC/SWPR and continue the workflow.

Thanks

Nabheet

former_member185167
Active Contributor
0 Kudos

If only I'd said that!

Former Member
0 Kudos

Thanks a lot!! SWPC solved the problem!!