Can somebody tell me how to change the TASK of a workflow to "CHANGE" mode, after it's been saved? Here, I find that once I create and save a task, I am unable to edit it.

Thanks,

Max.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi max_payne payne,

Go into the task and got the menu path then click change.

or go to PFTC and give the task number there and then goto menu path and click change.

Regards,

Balaji E.

Former Member
0 Kudos

Thanks balaji, yes, we can do that in PFTC. well, any idea if we can do the same in the same transaction of SWDD itself? here, the display<-->change option is always found to be deactivated!

Thanks,

MAX

Former Member
0 Kudos

Hi,

Doube click on the Taks no in SWDD it will take you to the Task definition

screen wherein you can make the changes.

Regards,

Manikandan R

former_member186746
Active Contributor
0 Kudos

Hi Max,

what version are you on, I remember that using SWDD for workflow modeling is not advised for 4.6c or older versions. I even heard of workflows disappearing and other strange stuff. It's advised to use PFTC for it.

Kind regards, Rob Dielemans

Answers (1)

Answers (1)

Former Member
0 Kudos

hi max_payne payne,

May i know what version of SAP you are using.

Regards

Balaji E.

Former Member
0 Kudos

Hi balaji, sorry for my late reply.

well, i am using ecc6.