Help: Configure the Prefix on PRD/Production system

glauco
Active Contributor
0 Kudos
97

Friends,

I´ve already created the prefix tasks for workflow on DEV and I´ve already transported it to QUA and PRD system.

But Now I have to test the workflow on PRD system, but when I went on SWU3, the system is saying that I have to configurate the prefix. When I went to the OOW4 to see on production/PRD, It´s already created but it is configured with the DEV system.

What can I do ?

Accepted Solutions (0)

Answers (1)

Answers (1)

keohanster
Active Contributor
0 Kudos

Hi Glauco,

In SWU3 in your PRD system, it is OK to have a yellow (or red) light for the configuring of task prefixes. You set your task prefix numbers in your DEV system and transport them up. Your task prefixes should remain consistent with what you set up in DEV all the way up the transport stream.

Cheers,

Sue