Hello Friends,

I have One BI system for that 5 source systems were connected .

In Our case Every plant use a "custom" Calendar like ZJ, Z5, ZI with different source systems.

All these "custom" calendars are not defined in a single source system, so when we make the Transfer of Factory Calendars we need to use the option "Rebuild tables" (the only option that works) that deletes all custom calendars from previous transferred other source system.

Then my question: is there any way to "add" (without deleting) these custom calendars to BI from all source systems ? (in order BI has all "custom" calendars)

If no, what's the solution to this problem?

Appreciate your answers.

Regards,

Gautam

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

two options.

a) maintain the factory calendars in BW itself and do no more replication from any source system

b) define one source system as a leading system for the replication and maintain all calendars there.

regards

Siggi

former_member182470
Active Contributor
0 Kudos

Hi,

You can use "Transfer Global Settings" option by right clicking your source systems in BI.

Hope this helps......