Hello. We are currently in the process of implementing the Enterprise Consolidation Transaction Data InfoCube (0ECCS_C01).

We are attempting to develop a data loading strategy for the InfoCube. Since this InfoCube does not have a delta process, reloading the entire cube on a daily basis is not feasable due to the length of time. We would like to set it up where it would load the current month for actuals plus into the future for forecast dollars.

Has anyone established a data loading process for their consolidated accounting InfoCube that works well and keeps data loading time to a minimum?

Best regards,

Lynn

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You could prepare packages:

one which you upload all data from previous years/months

second with OLAP variables (for example 0DAT) which you upload data only from present day/month/year - depends which variable you select (add this package to the chain).

When the second package will crash, you have to repeat procedure.

Regards,