Is it possible to delay a quarterly update to a SAC tenant?

For example, my peak period of trading is during the months of November and December and I do not want the November quarterly update to be applied to my SAC production tenant in case it causes any issues. Is it possible to request this to be delayed until after the peak period?

Accepted Solutions (0)

Answers (2)

Answers (2)

Stevie_M
Explorer
0 Kudos

Thanks Martijn

mfoeken
Active Contributor
0 Kudos

Hi Stephen,

We have managed to postpone wave updates a couple of times to avoid any changes to charging and allocation during MEC. However, this was on a bi-weekly release (or fast track tenant) and hosted in a SAP managed datacenter . I guess the standard answer would be that it's not possible but please contact your account representative from SAP as a starting point.

Kind regards,

Martijn van Foeken | Interdobs